Elevator / Elevator Installation Work Schedule
In high-rise buildings, the elevator is one of the most important vertical transportation tools for the mobilization of the occupants of the building. That's why generally there is always installation workelevator / elevatorin high-rise building projects.
Almost all elevator brands in Indonesia are imported goods made by factories abroad, so it takes a relatively long time for the production and delivery process.
Therefore, in the implementation of high-rise building construction projects, it is necessary to carry out the material agreement process as soon as possible so that elevator material reservations can be made to the factory.
This material approval process includes the submission of the elevator brand and its technical specifications, shop drawings, work procedures and implementation agenda. At least this process takes about 1 week.
After receiving the approval of the elevator material to be used, the process of ordering and fabricating the elevator can be carried out at the factory. The elevator fabrication process can take about 4 to 5 months.
After the end of fabrication, delivery will be carried out via maritime vessels which can take about 3 to 4 weeks including custom clearance.
From the port, delivery is carried out to the project site and the process of installing the lift unit is carried out. The process of installing the lift unit can take around 3 to 4 weeks.
So for elevator work from reservation to installation, it can take around 6 to 7 months. So it's similar to what we mentioned at the beginning of the article that the process of material agreement and elevator reservation must be as soon as possible because it takes quite a long time.
Elevator / Elevator Installation Work Schedule |
The schedule for the implementation of this elevator work is only a general description and may differ from the reality on the ground, because different brands may vary in the location of the country of manufacture and because the manufacturing process queues at the factory can also be longer.
Meanwhile, the installation of the lift unit is carried out after the completion of the pit lift and shaft lift structural work. So that the construction project implementation agenda and the elevator installation work agenda must be adjusted so that there are no delays.
That's a little review from rumahmaterial.com about the Elevator / Elevator Installation Work Schedule, so that it can be useful for you.